On Going Projects

 

Sl. No.

Name of the Schemes

Estimated cost
(Rs. in lac)

Upto date progress

1

Construction of road from Gholepukur to Tekhali Bridge via Amdabad High School (Part-A).

235.82

Ongoing

2

Construction of bituminous road from SBSTC bus stand to NH-41.

154.87

Ongoing

3

Land development work for bituminous road at Rajarampur Rehabilitation Colony (Part-A & Part-B). - E.W.

79.52

Ongoing

4

Construcion of concrete road from Brajalalchak Pramaniksura to Basanchak Bazar, Length-3.8 Km.

79.13

Ongoing

5

Construction of Moorum road at Baneshwarchak for diversion of existing moorum road inside proposed power plant CESC ltd.

106.08

Ongoing

6

Up-gradation of road & surface drain at Kumarchak-I block Rehabilitation Colony near 44 Flat Complex.

20.21

Ongoing

7

Up-gradation of road from moorum topping to bituminous surfacing at Priyambada Housing from Additional S.P.'s office to Basudevpur – 350 Mtr.

5.23

Ongoing

8

Up-gradation of road (bituminous) at Adani Wilmer road to HPL Link road with Box Culvert.

63.82

Ongoing

9

a) Construction of Bituminous Main Road at Chakdwipa Rehabilitation Colony (for WBM & Bituminous road).Total Length = 248.00 mtr.
b) Construction of Bituminous Branch Road at Chakdwipa Rehabilitation ColonyTotal Length = 195 mtr.

17.29

Ongoing

10

Purba Raghunathchak Rehabilitation Colony – Up-gradation of roads and remaining parts.

76.55

Ongoing

11

Construction of roads, drains & culverts at Bhabanipur Rehabilitation Colony, Phase-III.

119.77

Ongoing

12

Repairing of road from Sutahata bazaar to Hoerkhali.

87.05

Ongoing

13

Construction of concrete road from Dalimbachak Kaltala to Barobari Shibmandir via Adhikary Para.

72.32

Ongoing

14

Repairing of road from Biswanath Duttarchak more to Hatiberia Bus stand via Bharatiya Vidyabhawan School and Shataku Housing.

17.15

Ongoing

15

Plot filling at Bhabanipur Rehabilitation Colony, Phase-II.

19.27

Ongoing

16

Sinking of 12 nos. Tube Well at different places under Haldia Municipality - Funded from MPLADS.

13.39

Ongoing

17

Composite work for proposed District Head Quarter at Nimtouri Tamluk, Purba Medinipur. Phase-I : Construction of road. Phase-II : Construction of cross drainage work. Phase-III : Land Development work by carried earth and fly ash. Phase-IV : Construction

1668.70

Ongoing

18

Construction of Main College Building of 2nd campus of Dr. Meghnath Saha Institute of Technology, Haldia from foundation to 2nd floor along with sanitary plumbing works complete in all respects.

694.42

Ongoing

19

Repairing of Steel Bridge at Tentulberia on the road from Railway Crossing to Geonkhali Water Treatment Plant (Phase-I).

29.78

Ongoing

20

Miscellaneous civil works for renovation of Children's Park at Durgachak.

2.02

Ongoing

21

Construction of Boundary Wall at Haldia Trade Centre, Ranichack Haldia.

20.15

Ongoing

22

Painting of boundary wall including necessary repairing and re-construction at Haldia Bhawan.

3.08

Ongoing

23

Durgachak Super Market – Miscellaneous works such as Drain, Cover Slab, Sanitary, Plumbing etc.

6.57

Ongoing

24

Additional work for repairing and strengthening of Steel Bridge at Tentulberia on the road from Railway Crossing to Geonkhali Water Treatment Plant (Phase-II).

25.76

Ongoing

25

Electrification of Maharaja Nandakumar College

1.98

Ongoing

26

Electrification work of Food Park (Including electrical Connection).

124.15

Ongoing

27

Shifting of 11 K.V O.H line from the proposed site of lions Club, Vocational Training Institute & Paranchak high school at purba srikrishnapur, Haldia.

8.23

Ongoing

28

Electrification of Chakdwipa Rehabilitation Colony.

0.25

Ongoing

29

Electrification of Block E, F & G of Purba Srikrishnapur, Rehabilitation Colony.

18.39

Ongoing

30

Conversion of Bulk power supply to L & MV power supply at Staff Quarter, Tribeni sangam and other similar Building attached with the Geonkhali Water Treatment Plant.

17.45

Ongoing

31

Extension of existing grid at Basanchak, Barbajitpur, Banskona Jalpai under Haldia Panchayat Samity.

5.04

Ongoing

32

Electrification of Bar-Mohanpur and Hariballavpur under Sutahata Panchayat Samity

4.60

Ongoing

33

Electrification of Ramchandrapur, Barada & Bijayrampur under Sutahata Panchayat Samity

5.85

Ongoing

34

Electrification of Monirampur Netaji Sangha, Monirampur Manasa Mandir under Sutahata Panchayat Samity

5.58

Ongoing

35

Electrification of Gobindapur Chakraborty Para and Bhowmick Para and Anarpur under Sutahata Panchayat Samity

5.16

Ongoing

36

Extension of existing grid at Barbasudevpur Kuity Para, Chaulkhola Daspara, Gorankhali & Jamberia, Iswardha Jalpai, Malpara (Dwariberia), Brajalalchak (Palpara west side) under Haldia Panchayat Samity.

3.91

Ongoing

37

Extension of existing grid at Gorankhali, Sapua, Barbasudevpur, Suklalchak, Hadia under Haldia Panchayat Samity.

2.18

Ongoing

38

Electrification of Barbajitpur 43 No. Booth Paul / Sk. Para (Dakshin Pally) (59), Barbajitpur 44 No. Booth Das Pally to Sitala Mandir / Sk. Para (59), Barabari Dakshin Pally and Paschim Pally (60), Chaulkhaola Dakshin near sushil Samanta’s house (93), Barsuklalchak Din Para, Dwariberia (P.S. Sutaha), Banskhana Jalpai (Beltala), P.S. Bhabanipur, Dalimbachak Patra Pally (Kumarpur) under Haldi Panchayet Samity.

14.67

Ongoing

39

Installation Road Traffic Signal System at Brajalalchak, Manjushree, Chaitnyapur,Ranichak

22.71

Ongoing

40

Drawal of 11KV Line from Manoharpur to Chaulkhola Daspara

3.38

Ongoing

 

 

 